Weekly Acme update

reports/01_weekly-status-thread.txt

Read the source in context.

Thread dates and speakers remain part of the record. A removed line is no longer available in this workspace.

1*** SYNTHETIC DATA. Entirely fictional. Acme Org, Meridian Consulting and every
2*** person named are invented. Generated for the RELEX challenge track,
3*** AaltoAI Hackathon 2026.
4
5Subject: Weekly Acme update
6From: Ana Duarte <ana.duarte@relexsolutions.example>
7Date: Monday, April 6, 2026 17:30
8To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
9Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
10Messages in thread: 18
12Hi All,
14Hereby the weekly update.
16Update 06-04-2026 (Week 15)
17🟢 On Track
19Q1 fresh waste 3.4% against a 4.1% baseline. Detail in a separate note.
21Timeline
22On plan.
24[Image removed by sender]
26Topics worked on last week
271. Q1 results compiled
29Topics planned for this week
301. Present Q1 results
311. Bakery build continues
33If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
35Kind regards,
37Best regards,
38Ana Duarte
39Project Manager Image
40+351 913 882 145 | UTC +01:00
41ana.duarte@relexsolutions.example
42Rua do Ouro 42, 1100-063 Lisboa
43Connect with me
44Image
45Image
46Plan better. Sell more. Waste less
47relexsolutions.example Image
48LinkedInYouTube
51From: Ana Duarte <ana.duarte@relexsolutions.example>
52Sent: Monday, March 9, 2026 16:35
53To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
54Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
55Subject: Re: Weekly Acme update
57Hi All,
59Hereby the weekly update.
61Update 09-03-2026 (Week 11)
62🟢 On Track
64Timeline
65Bakery workstream started.
67[Image removed by sender]
69Topics worked on last week
701. Bakery interface points agreed
712. Q1 measurement approach drafted
723. Nightly article extract completed, no errors
74Topics planned for this week
751. Bakery build begins
762. Prepare Q1 results
78If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
80Kind regards,
82Best regards,
83Ana Duarte
84Project Manager Image
85+351 913 882 145 | UTC +01:00
86ana.duarte@relexsolutions.example
87Rua do Ouro 42, 1100-063 Lisboa
88Connect with me
89Image
90Image
91Plan better. Sell more. Waste less
92relexsolutions.example Image
93LinkedInYouTube
96From: Ana Duarte <ana.duarte@relexsolutions.example>
97Sent: Monday, February 9, 2026 17:15
98To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
99Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
100Subject: Re: Weekly Acme update
102Hi All,
104Hereby the weekly update.
106Update 09-02-2026 (Week 7)
107🟡Slight Delay
109Risk
110DC-2 feed failed twice in January. Less often than before go-live but still failing.
112Timeline
113Bakery scoping slower than planned.
115[Image removed by sender]
117Topics worked on last week
1181. Meridian onboarded
1192. Interface points drafted
1203. Nightly article extract completed, no errors
122Topics planned for this week
1231. Finalise bakery interface definition
125Potential risk identified 🟡Slight Delay
1261. DC-2 feed failed twice in January. Less often than before go-live but still failing.
128If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
130Kind regards,
132Best regards,
133Ana Duarte
134Project Manager Image
135+351 913 882 145 | UTC +01:00
136ana.duarte@relexsolutions.example
137Rua do Ouro 42, 1100-063 Lisboa
138Connect with me
139Image
140Image
141Plan better. Sell more. Waste less
142relexsolutions.example Image
143LinkedInYouTube
146From: Ana Duarte <ana.duarte@relexsolutions.example>
147Sent: Monday, January 12, 2026 16:50
148To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
149Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
150Subject: Re: Weekly Acme update
152Hi All,
154Hereby the weekly update.
156Update 12-01-2026 (Week 3)
157🟢 On Track
159Timeline
160Four weeks live.
162[Image removed by sender]
164Topics worked on last week
1651. Holiday period passed without incident
1662. Nightly article extract completed, no errors
168Topics planned for this week
1691. Bakery workstream scoping with Meridian
1702. Baseline reporting for Q1
172If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
174Kind regards,
176Best regards,
177Ana Duarte
178Project Manager Image
179+351 913 882 145 | UTC +01:00
180ana.duarte@relexsolutions.example
181Rua do Ouro 42, 1100-063 Lisboa
182Connect with me
183Image
184Image
185Plan better. Sell more. Waste less
186relexsolutions.example Image
187LinkedInYouTube
190From: Ana Duarte <ana.duarte@relexsolutions.example>
191Sent: Monday, December 22, 2025 15:40
192To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
193Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
194Subject: Re: Weekly Acme update
196Hi All,
198Hereby the weekly update.
200Update 22-12-2025 (Week 52)
201🟢 On Track
203Last update before the break. Next one 12 January.
205Timeline
206Live since 15 December. First week clean.
208[Image removed by sender]
210Topics worked on last week
2111. Fresh go-live for produce, dairy and chilled ready meals (Phase 5 - Deployment)
213Topics planned for this week
2141. Monitor over the holiday period
216If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
218Kind regards,
220Best regards,
221Ana Duarte
222Project Manager Image
223+351 913 882 145 | UTC +01:00
224ana.duarte@relexsolutions.example
225Rua do Ouro 42, 1100-063 Lisboa
226Connect with me
227Image
228Image
229Plan better. Sell more. Waste less
230relexsolutions.example Image
231LinkedInYouTube
234From: Ana Duarte <ana.duarte@relexsolutions.example>
235Sent: Monday, December 8, 2025 17:00
236To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
237Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
238Subject: Re: Weekly Acme update
240Hi All,
242Hereby the weekly update.
244Update 08-12-2025 (Week 50)
245🟢 On Track
247Timeline
248On plan for 15 December.
250[Image removed by sender]
252Topics worked on last week
2531. Cutover checklist walked (Phase 5 - Deployment)
2542. Rollback tested (Phase 5 - Deployment)
256Topics planned for this week
2571. Go live 15 December
2582. First week support
260If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
262Kind regards,
264Best regards,
265Ana Duarte
266Project Manager Image
267+351 913 882 145 | UTC +01:00
268ana.duarte@relexsolutions.example
269Rua do Ouro 42, 1100-063 Lisboa
270Connect with me
271Image
272Image
273Plan better. Sell more. Waste less
274relexsolutions.example Image
275LinkedInYouTube
278From: Ana Duarte <ana.duarte@relexsolutions.example>
279Sent: Monday, November 24, 2025 16:20
280To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
281Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
282Subject: Re: Weekly Acme update
284Hi All,
286Hereby the weekly update.
288Update 24-11-2025 (Week 48)
289🟢 On Track
291Note that the plan has been reissued on a two delivery basis. Earlier plan documents showing three waves for fresh are superseded and should not be used.
293Timeline
294Replanned. Go-live 15 December for three categories.
296[Image removed by sender]
298Topics worked on last week
2991. Go/no-go held. Produce, dairy and chilled approved. Bakery descoped
3002. OP_ID field exclusion agreed and confirmed in writing
302Topics planned for this week
3031. Cutover preparation (Phase 5 - Deployment)
3042. Store communications
306If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
308Kind regards,
310Best regards,
311Ana Duarte
312Project Manager Image
313+351 913 882 145 | UTC +01:00
314ana.duarte@relexsolutions.example
315Rua do Ouro 42, 1100-063 Lisboa
316Connect with me
317Image
318Image
319Plan better. Sell more. Waste less
320relexsolutions.example Image
321LinkedInYouTube
324From: Ana Duarte <ana.duarte@relexsolutions.example>
325Sent: Monday, November 10, 2025 17:45
326To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
327Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
328Subject: Re: Weekly Acme update
330Hi All,
332Hereby the weekly update.
334Update 10-11-2025 (Week 46)
335🟡Slight Delay
337Risk
338Bakery recommendation is to descope. This changes the Phase 2 shape.
340Timeline
341Four weeks behind. Go/no-go next week.
343[Image removed by sender]
345Topics worked on last week
3461. UAT results compiled (Phase 4 - Testing)
3472. Recommendation drafted
349Topics planned for this week
3501. Go/no-go call Monday
352Potential risk identified 🟡Slight Delay
3531. Bakery recommendation is to descope. This changes the Phase 2 shape.
355If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
357Kind regards,
359Best regards,
360Ana Duarte
361Project Manager Image
362+351 913 882 145 | UTC +01:00
363ana.duarte@relexsolutions.example
364Rua do Ouro 42, 1100-063 Lisboa
365Connect with me
366Image
367Image
368Plan better. Sell more. Waste less
369relexsolutions.example Image
370LinkedInYouTube
373From: Ana Duarte <ana.duarte@relexsolutions.example>
374Sent: Monday, October 27, 2025 16:30
375To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
376Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
377Subject: Re: Weekly Acme update
379Hi All,
381Sorry for the delay in the weekly update!
383Hereby the weekly update.
385Update 27-10-2025 (Week 44)
386🟡Slight Delay
388Risk
389Bakery accuracy poor. Likely a scope change rather than a defect.
391Timeline
392Four weeks behind. Holding.
394[Image removed by sender]
396Topics worked on last week
3971. UAT nine working days complete (Phase 4 - Testing)
3982. Bakery assessed as mostly bake-off
400Topics planned for this week
4011. Prepare go/no-go recommendation
403Potential risk identified 🟡Slight Delay
4041. Bakery accuracy poor. Likely a scope change rather than a defect.
406If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
408Kind regards,
410Best regards,
411Ana Duarte
412Project Manager Image
413+351 913 882 145 | UTC +01:00
414ana.duarte@relexsolutions.example
415Rua do Ouro 42, 1100-063 Lisboa
416Connect with me
417Image
418Image
419Plan better. Sell more. Waste less
420relexsolutions.example Image
421LinkedInYouTube
424From: Ana Duarte <ana.duarte@relexsolutions.example>
425Sent: Monday, October 13, 2025 17:08
426To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
427Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
428Subject: Re: Weekly Acme update
430Hi All,
432Hereby the weekly update.
434Update 13-10-2025 (Week 42)
435🟡Slight Delay
437Risk
438Sofia Almeida unavailable from today until mid November. She is our only source of category knowledge on fresh, so UAT findings that need her judgement will queue.
440Timeline
441Four weeks behind. Two weeks recovered.
443[Image removed by sender]
445Topics worked on last week
4461. UAT running on produce, dairy and chilled (Phase 4 - Testing)
448Topics planned for this week
4491. Continue UAT (Phase 4 - Testing)
4502. Bakery assessment
452Potential risk identified 🟡Slight Delay
4531. Sofia Almeida unavailable from today until mid November. She is our only source of category knowledge on fresh, so UAT findings that need her judgement will queue.
455If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
457Kind regards,
459Best regards,
460Ana Duarte
461Project Manager Image
462+351 913 882 145 | UTC +01:00
463ana.duarte@relexsolutions.example
464Rua do Ouro 42, 1100-063 Lisboa
465Connect with me
466Image
467Image
468Plan better. Sell more. Waste less
469relexsolutions.example Image
470LinkedInYouTube
473From: Ana Duarte <ana.duarte@relexsolutions.example>
474Sent: Monday, September 29, 2025 16:55
475To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
476Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
477Subject: Re: Weekly Acme update
479Hi All,
481Hereby the weekly update.
483Update 29-09-2025 (Week 40)
484🔴 Risk
486Risk
487Still six weeks behind. Recovery depends on UAT throughput over October.
489Timeline
490Recovering. Six weeks behind, holding rather than slipping further.
492[Image removed by sender]
494Topics worked on last week
4951. Defect fixed and verified (Phase 2 - Technical Implementation)
4962. Solution consultant onboarded
498Topics planned for this week
4991. UAT on produce and dairy (Phase 4 - Testing)
5002. Prepare go/no-go for November
502Potential risk identified 🔴 Risk
5031. Still six weeks behind. Recovery depends on UAT throughput over October.
505If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
507Kind regards,
509Best regards,
510Ana Duarte
511Project Manager Image
512+351 913 882 145 | UTC +01:00
513ana.duarte@relexsolutions.example
514Rua do Ouro 42, 1100-063 Lisboa
515Connect with me
516Image
517Image
518Plan better. Sell more. Waste less
519relexsolutions.example Image
520LinkedInYouTube
523From: Ana Duarte <ana.duarte@relexsolutions.example>
524Sent: Monday, September 15, 2025 17:22
525To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
526Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
527Subject: Re: Weekly Acme update
529Hi All,
531Hereby the weekly update.
533Update 15-09-2025 (Week 38)
534🔴 Risk
536Risk
537Fresh Phase 2 six weeks behind. Two causes: Acme UAT resourcing, and a calculation defect producing negative quantities in test. Both being addressed.
539Timeline
540Six weeks behind on the fresh workstream.
542[Image removed by sender]
544Topics worked on last week
5451. Escalation call held Friday
5462. Approximation approach agreed internally (Phase 3 - Business Configuration)
548Topics planned for this week
5491. Fix the negative quantity defect (Phase 2 - Technical Implementation)
5502. Add a consultant to drive UAT (Phase 4 - Testing). Nadia is confirmed
552Potential risk identified 🔴 Risk
5531. Fresh Phase 2 six weeks behind. Two causes: Acme UAT resourcing, and a calculation defect producing negative quantities in test. Both being addressed.
555If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
557Kind regards,
559Best regards,
560Ana Duarte
561Project Manager Image
562+351 913 882 145 | UTC +01:00
563ana.duarte@relexsolutions.example
564Rua do Ouro 42, 1100-063 Lisboa
565Connect with me
566Image
567Image
568Plan better. Sell more. Waste less
569relexsolutions.example Image
570LinkedInYouTube
573From: Ana Duarte <ana.duarte@relexsolutions.example>
574Sent: Monday, September 1, 2025 16:40
575To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
576Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
577Subject: Re: Weekly Acme update
579Hi All,
581Hereby the weekly update.
583Update 01-09-2025 (Week 36)
584🟡Slight Delay
586Question
587Still open from four updates ago. We are now proceeding on an approximation unless we hear otherwise this week.
589Risk
590Shelf life unresolved. Proceeding on an approximation so the build is not blocked.
592Timeline
593Holding.
595[Image removed by sender]
597Topics worked on last week
5981. Drafted an approximation approach for remaining shelf life (Phase 3 - Business Configuration)
600Topics planned for this week
6011. Put shelf life on the escalation agenda
6021. Begin UAT preparation (Phase 4 - Testing)
604Potential risk identified 🟡Slight Delay
6051. Shelf life unresolved. Proceeding on an approximation so the build is not blocked.
607If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
609Kind regards,
611Best regards,
612Ana Duarte
613Project Manager Image
614+351 913 882 145 | UTC +01:00
615ana.duarte@relexsolutions.example
616Rua do Ouro 42, 1100-063 Lisboa
617Connect with me
618Image
619Image
620Plan better. Sell more. Waste less
621relexsolutions.example Image
622LinkedInYouTube
625From: Nadia Haddad <n.haddad@relexsolutions.example>
626Sent: Monday, August 18, 2025 17:05
627To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
628Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
629Subject: Re: Weekly Acme update
631Hi All,
633Hereby the weekly update.
635Update 18-08-2025 (Week 34)
636🟡Slight Delay
638Question
639Repeating from the last two updates. Is remaining shelf life stored anywhere, and if not, is goods receipt date available outside the WMS?
641Risk
642Shelf life now four weeks open. Approaching the point where we need a workaround.
644Timeline
645Holding. The plan assumes shelf life resolves in August.
647[Image removed by sender]
649Topics worked on last week
6501. Chilled ready meals structure loaded (Phase 3 - Business Configuration)
6512. Shelf life field mapping (Phase 2 - Technical Implementation) NOT FINISHED
653Topics planned for this week
6541. Shelf life escalation to steering
656Potential risk identified 🟡Slight Delay
6571. Shelf life now four weeks open. Approaching the point where we need a workaround.
659If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
661Kind regards,
663Nadia Haddad
664Solution Consultant Image
665+46 76 552 30 18 | CET
666n.haddad@relexsolutions.example
667Vasagatan 7, 111 20 Stockholm
668Image
669Plan better. Sell more. Waste less
670relexsolutions.example
673From: Ana Duarte <ana.duarte@relexsolutions.example>
674Sent: Monday, August 4, 2025 16:15
675To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
676Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
677Subject: Re: Weekly Acme update
679Hi All,
681Sorry for the delay in the weekly update!
683Hereby the weekly update.
685Update 04-08-2025 (Week 32)
686🟡Slight Delay
688Question
689We need remaining shelf life at the point of order, per article per site. MARA-MHDHB appears to be total shelf life rather than remaining. Is remaining life stored anywhere, and if not, is goods receipt date available outside the WMS?
691Risk
692Shelf life still unresolved. Acme warehouse team unavailable.
694Timeline
695Two weeks of float used.
697[Image removed by sender]
699Topics worked on last week
7001. Configuration continues on the parts that do not need shelf life (Phase 3 - Business Configuration)
702Topics planned for this week
7031. Escalate shelf life if no answer this week (Phase 2 - Technical Implementation)
705Potential risk identified 🟡Slight Delay
7061. Shelf life still unresolved. Acme warehouse team unavailable.
708If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
710Kind regards,
712Best regards,
713Ana Duarte
714Project Manager Image
715+351 913 882 145 | UTC +01:00
716ana.duarte@relexsolutions.example
717Rua do Ouro 42, 1100-063 Lisboa
718Connect with me
719Image
720Image
721Plan better. Sell more. Waste less
722relexsolutions.example Image
723LinkedInYouTube
726From: Ana Duarte <ana.duarte@relexsolutions.example>
727Sent: Monday, July 21, 2025 17:30
728To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
729Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
730Subject: Re: Weekly Acme update
732Hi All,
734Hereby the weekly update.
736Update 21-07-2025 (Week 30)
737🟡Slight Delay
739Question
740We need remaining shelf life at the point of order, per article per site. MARA-MHDHB appears to be total shelf life rather than remaining. Is remaining life stored anywhere, and if not, is goods receipt date available outside the WMS?
742Risk
743Shelf life field mapping unresolved for two weeks. Blocks the ordering logic.
745Timeline
746One week of float used. Not yet a concern.
748[Image removed by sender]
750Topics worked on last week
7511. Produce and dairy configuration 60% complete (Phase 3 - Business Configuration)
7522. Shelf life field mapping (Phase 2 - Technical Implementation) NOT FINISHED
754Topics planned for this week
7551. Chase shelf life for the second time (Phase 2 - Technical Implementation)
757Potential risk identified 🟡Slight Delay
7581. Shelf life field mapping unresolved for two weeks. Blocks the ordering logic.
760If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
762Kind regards,
764Best regards,
765Ana Duarte
766Project Manager Image
767+351 913 882 145 | UTC +01:00
768ana.duarte@relexsolutions.example
769Rua do Ouro 42, 1100-063 Lisboa
770Connect with me
771Image
772Image
773Plan better. Sell more. Waste less
774relexsolutions.example Image
775LinkedInYouTube
778From: Ana Duarte <ana.duarte@relexsolutions.example>
779Sent: Monday, July 7, 2025 16:48
780To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
781Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
782Subject: Re: Weekly Acme update
784Hi All,
786Hereby the weekly update.
788Update 07-07-2025 (Week 28)
789🟢 On Track
791Timeline
792On track.
794[Image removed by sender]
796Topics worked on last week
7971. Fresh category structure loaded for produce and dairy (Phase 3 - Business Configuration)
7982. Shelf life request sent to Priya (Phase 2 - Technical Implementation)
800Topics planned for this week
8011. Continue category configuration (Phase 3 - Business Configuration)
8021. Await shelf life mapping (Phase 2 - Technical Implementation)
804If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
806Kind regards,
808Best regards,
809Ana Duarte
810Project Manager Image
811+351 913 882 145 | UTC +01:00
812ana.duarte@relexsolutions.example
813Rua do Ouro 42, 1100-063 Lisboa
814Connect with me
815Image
816Image
817Plan better. Sell more. Waste less
818relexsolutions.example Image
819LinkedInYouTube
822From: Ana Duarte <ana.duarte@relexsolutions.example>
823Sent: Monday, June 30, 2025 17:12
824To: Lena Fischer <lena.fischer@acme-org.example>; Priya Nair <priya.nair@acme-org.example>
825Cc: Marco Rossi <marco.rossi@relexsolutions.example>; Nadia Haddad <n.haddad@relexsolutions.example>; Tomas Lindholm <tomas.lindholm@relexsolutions.example>
826Subject: Weekly Acme update
828Hi All,
830Hereby the weekly update.
832Update 30-06-2025 (Week 27)
833🟢 On Track
835Last week we had our kick-off for the fresh Phase 2 workstream. In addition to the status call, we will send this summary email each Monday.
837Timeline
838Kick-off complete. We are on the plan as drawn.
840[Image removed by sender]
842Topics worked on last week
8431. Phase 2 scope confirmed against the June steering (Phase 1 - Project Initiation & Specification)
8442. Requested the shelf life field from Acme IT (Phase 2 - Technical Implementation)
846Topics planned for this week
8471. Begin fresh category configuration (Phase 3 - Business Configuration)
8482. Chase the shelf life field mapping (Phase 2 - Technical Implementation)
850If there is anything else you'd like to see in these update emails, please don't hesitate to let us know.
852Kind regards,
854Best regards,
855Ana Duarte
856Project Manager Image
857+351 913 882 145 | UTC +01:00
858ana.duarte@relexsolutions.example
859Rua do Ouro 42, 1100-063 Lisboa
860Connect with me
861Image